CRaTER Pre-Ship Review

MIT Room NE80-6100

1 Hampshire Street, Cambridge, MA

January 3-4, 2008

Presentations highlighted in Green are Final

Day 1
Topic from Review Team

PDF

Presenter
9:00 am
Instrument PSR Summary of Objectives
X
Review Team
9:15 am
Instrument Configuration
X
Bob Goeke
9:45 am
Instrument Calibration
Science Requirements Compliance

X
Justin Kasper
10:45 am
RFA Status
X
Bob Goeke
11:15 am
Compliance with PAIP
Safety/Certification Compliance
RFA's from prior reviews
Failure Reports/Waivers/MRBs/Inspections

X
Brian Klatt
noon
Lunch


1:00 pm

Results of Qualification Tests
Results of Functional Testing
Performance Margins

X

Bob Goeke

2:00 pm
Thermal Balance and Modeling
X
Christine Cottingham

Extended Thermal Modeling
X
Eric O'Day
2:30 pm
Contamination Control
Shipping/Handling/Logistics
Spares/Maintenance Plan

X
Rick Foster
3:00 pm
Installation Procedures
Orbiter Level Test Procedures

X
Bob Goeke with
   Project Inputs
3:30 pm
Caucus

Review Team
Day 2
Topic from Review Team

PDF

Presenter
9:00 am
  -> noon
Review Team schedule margin




Reference Documents: