CRaTER

Pre-Environmental Review

MIT Room NE80-6100

1 Hampshire Street, Cambridge, MA

September 10-11, 2007

Presentations highlighted in Green are Final

Day 1
Topic from GSFC-STD-1001

PDF

Presenter
1300
Instrument PER Summary of Objectives
X
Review Team
1315 Science Requirements Update
X
Justin Kasper
1345 Engineering Requirements/Design Update X
Bob Goeke
1400

Completed Verification Results

X

Bob Goeke

1415 Safety
X
Brian Klatt
1430 Risk Management
X
Rick Foster
1500 Assurance Activities
X
Brian Klatt
1530
Calibration Test Planning XJustin Kasper
1615Mission Operations X
Mike Golightly
Day 2
Topic from GSFC-STD-1001
PDF
Presenter
0900Programmatics
X

Rick Foster

0930
Project and Independent Review Activity
X
Rick Foster
0945
Spacecraft Interfaces X
Bob Goeke
1000

Environmental Test Planning

  • EMI
  • Vibration
  • Thermal-Vacuum
X
Bob Goeke
Dorothy Gordon
Eric O'Day
Matt Smith
1130
Spacecraft I&T X
Mike Golightly
1200 Review Team Caucus


1300 Closing Remarks

Review Team


Reference Documents:
Internal Utilities: